Which of the following refers to the time in which an activity can be completed without delaying the project?

Which of the following refers to the time in which an activity can be completed without delaying the project?

C) The latest expected completion time refers to the time in which an activity can be completed without delaying the project.

What is defined as the duration of time that an activity can be delayed without delaying the project’s estimated completion time and without delaying the start of any succeeding activity?

The term Late Finish refers to the latest time an activity may begin without delaying the completion of the project. Before calculating a Late Start time for an activity, the Late Finish time must be known.

What is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date?

FloatThe amount of time an activity can be delayed from an early start without delaying the completion date., sometimes called slack, is the amount of time an activity, network path, or project can be delayed from the early start without changing the completion date of the project.

Is a visual device that shows the duration of tasks in a project?

A Gantt chart is a visual device that shows the duration of tasks in a project. It is a low-cost means of ensuring that (1) all activities are planned for, (2) their order of performance is planned for, (3) the activity times are recorded, and (4) the overall project time is developed.

Which term is used for the amount of time an activity can be delayed without delaying the early start date of any immediately following activities?

FREESLACK

What is an activity start date?

The early start date for an activity is the earliest date the activity can begin. The estimate considers durations and resource availability calendars. To calculate early start dates, begin with the project start date and assign that date as the start date of activities that have no predecessor activities.

What is earliest start time and latest start time?

Early Start Time: The earliest point in the schedule at which a task can begin. Early Finish Time: The earliest point in the schedule at which a task can finish. Latest Start Time: The latest point in the schedule at which a task can start without causing a delay.

What is late schedule of a project?

The early start, early finish, late start, and late finish dates of a project schedule are the primary dates that are calculated in any project schedule. These calculations are based on a fixed duration. Late Finish represents the latest date an activity can finish, without delaying the finish of the project.